02 февраля 2011 Новости со строительства проекта Avatara Mae Phim, Районг Building A:
•
• Tiling works in floors 2,3,4,5,6 complete, 7 floor nearly complete
• Aluminum door installation ongoing
• Block works and plastering in shop house units and ground floor area
• Plastering works on roof including swimming pool
• Block works at fire stairs
• Outside plastering ongoing
• Electrical and sanitary piping follows block works
• Building B:
•
• Pile cap foundation completed
• Ground floor beams work has started